Before you take possession of a flat in Chennai, ask the builder one question: does the building have a completion certificate? In Tamil Nadu, this certificate isn't a formality. It confirms that the building was built as per the plan the authority approved, and the state's building rules make permanent electricity, water and sewer connections depend on it.
What is a completion certificate?
A completion certificate (CC) is issued by the authority that gave the planning permission, such as CMDA, DTCP or the local body, after the building is finished. It certifies that the building was constructed as per the approved plan. Newspapers and some documents also call it an occupancy certificate.
The rules are in Rule 20 of the Tamil Nadu Combined Development and Building Rules, 2019 (TNCDBR), which came into force in February 2019.
Which buildings need one?
Rule 20 applies to all buildings except:
- Small residential buildings: up to 12 m in height, with no more than 3 dwelling units or 750 sq m.
- Industrial buildings.
In practice, almost every apartment project in Chennai needs a CC. An independent house or a building with up to three flats, within the height and area limits, doesn't.
Why it matters: power, water and sewer connections
Rule 20(11) is the part that affects buyers most:
- Temporary water, electricity or sewer connections used during construction must not continue after the building is complete.
- No permanent connection to the water mains, sewer line or electricity network may be made without the authority's permission and a completion certificate.
The Madras High Court has upheld this link. It has held that water and electricity connections should be contingent on the completion certificate, and that builders cannot ask courts to order connections without one. Tangedco has also required CCs for new service connections, while small buildings that are exempt under the rules don't need one.
If a builder offers possession while the building runs on a temporary construction power supply, ask when the CC will be issued and get the date in writing.
How the certificate is issued
- During construction: a registered professional certifies progress at plinth level and at the last storey, and the authority checks for deviations from the approved plan.
- At completion: the owner or developer files a completion report (Form 5, with Forms 6 to 8), with confirmation of a Lift Inspector's certificate for lifts and a Fire and Rescue Services certificate for fire safety where needed.
- Inspection: the authority inspects the building to confirm it matches the approved plan.
- Decision: the authority must communicate its decision within 30 days of receiving a complete application.
- Phased projects: where a project has several buildings, the authority can certify individual completed blocks.
Unauthorised construction or a change of use after the CC lets the authority discontinue services.
Buyer checklist
- Ask for a copy of the CC before you pay the final instalment or take possession, and check that the block and tower numbers match your flat.
- Match it to the approved plan. The CC covers the building as approved. Extra floors, enclosed balconies or converted parking may not be covered.
- Check the permanent connections: a regular electricity service connection in the association's or owners' names, and Metrowater or local-body water and sewer connections.
- Look up the project on TNRERA. See how to check TNRERA registration.
- Resale flats: ask the seller for the CC along with the parent documents. Without it, the building may not have permanent service connections.
- Small buildings: if the building is exempt (up to 12 m, 3 units or 750 sq m), keep a copy of the approved plan instead. See self-certification for building permits.
For the rest of the handover, use our possession checklist for new flats and our guide to under-construction vs ready-to-move flats.
Frequently asked questions
This article explains the rules in general terms and isn't legal advice. For a specific property, have a lawyer check the approvals and certificates.
Sources
- Indian Kanoon: Rule 20, Tamil Nadu Combined Development and Building Rules, 2019 — Exemptions, Form 5, inspections, 30-day decision, sub-rule 11 on service connections
- Indian Kanoon: Rule 20(11), connections to sewer, water mains or electricity — No permanent connections without a completion certificate
- Town and Country Planning, Tamil Nadu: TNCDBR 2019, Part IV (Completion Certificate) — Official rules document
- Indian Kanoon: Madras High Court on connections without a completion certificate — Connections contingent on completion; builders can't seek mandamus without a CC
- DT Next: Power supply only after building completion certificate — TNCDB Rules 2019 in force from 4 February 2019
- DT Next: No completion certificate for small buildings, Tangedco — Exemption for residential buildings up to 12 m
- Housing.com: No electricity to housing projects without completion certificate, rules Madras HC — April 2018 government order and HC ruling